what rule determines when the staging process ends?

An EMC NetWorker server has been configured to stage an adv_file type device upon reaching an
high water mark of 80%. After the staging begins, what rule determines when the staging process
ends?

A.
The capacity must fall below the low water mark

B.
The capacity must fall below the high water mark

C.
The adv_file type device must be empty

D.
The predefined amount of data is moved