What is the purpose of ‘fallback’ when CPP is enabled?

What is the purpose of ‘fallback’ when CPP is enabled?

A.
Will reset storage settings to CPM

B.
Will downgrade the CentraStar software

C.
When there are not enough nodes available in any cube for writing, an error is generated

D.
When there are enough nodes available, a question will be asked as to which storage,
CPP/CPM