what is the maximum time to recommend to the customer?

A customer has decided on EMC Avamar as a solution. They are interested in the replication
features to accommodate multiple off-site locations. The customer wants to know the longest time
they can run replication.
According to EMC best practices, what is the maximum time to recommend to the customer?

PrepAway - Latest Free Exam Questions & Answers

A.
6 Hours

B.
8 Hours

C.
12 Hours

D.
16 Hours