A customer has decided on EMC Avamar as a solution. They are interested in the replication
features to accommodate multiple off-site locations. The customer wants to know the longest time
they can run replication.
According to EMC best practices, what is the maximum time to recommend to the customer?
A.
6 Hours
B.
8 Hours
C.
12 Hours
D.
16 Hours