CompTIA Exam Questions

Which of the following would BEST mitigate the risk of injury to those team members, without affecti

During execution, a project manager of a construction project requires certain project team members to work outdoors, atop tall buildings. Which of the following would BEST mitigate the risk of injury to those team members, without affecting the approved project schedule?

A.
Ensure that project team members do not work in very windy weather.

B.
Ensure that project team members are furnished with slip-resistant boots.

C.
Ensure that project team members are trained in injury response.

D.
Ensure that project team members are covered by applicable insurance.