Which of the following would be MOST helpful in creating project roles and resource requirements?

Which of the following would be MOST helpful in creating project roles and resource
requirements?

A.
Work Breakdown Structure

B.
Human Resources Plan

C.
Project Charter

D.
Responsibility Assignment Matrix