CompTIA Exam Questions

Which of the following tools is the project manager utilizing?

A project manager is performing activity sequencing with the project team. Each activity is written in a box with arrows linking the boxes according to their dependencies. Which of the following tools is the project manager utilizing?

A.
Arrow Diagramming Method (ADM)

B.
Precedence Diagramming Method (PDM)

C.
Critical Path Method (CPM)

D.
Critical Chain Method (CCM)