CompTIA Exam Questions

Which of the following should the project manager do to gather this information?

A project manager needs to determine how much it will cost for a third party to complete
certain deliverables and the steps they will take to complete those deliverables. Which of
the following should the project manager do to gather this information?

A.
Issue an RFP

B.
Create a WBS

C.
Develop a SOW

D.
Issue an RFQ