Which of the following represents the EAC of an ongoing project with an AC of $100,000, a CV of $10

Which of the following represents the EAC of an ongoing project with an AC of $100,000, a CV of

$10,000 and an ETC of $50,000?

A.
$90,000

B.
$140,000

C.
$150,000

D.
$160,000