CompTIA Exam Questions

Which of the following may have a significant adverse impact upon the successful completion of an in

Which of the following may have a significant adverse impact upon the successful completion of an international project? (Select THREE).

A.
Time zones

B.
Travel costs

C.
Co-location of resources

D.
The project plan

E.
Scheduled vacations

F.
Language barriers