Which of the following is the project’s CPI? seenagape 9 years ago The project has spent $5,000 to date. The earned value of the project is $7,500. Which ofthe following is the project’s CPI? A. -$2,500 B. $12,500 C. 0.67 D. 1.5 ← Previous question Next question →