CompTIA Exam Questions

Which of the following is the project’s CPI?

The project has spent $5,000 to date. The earned value of the project is $7,500. Which of
the following is the project’s CPI?

A.
-$2,500

B.
$12,500

C.
0.67

D.
1.5