CompTIA Exam Questions

which of the following is the MOST important task of the project sponsor?

In order to complete the pre-project setup, which of the following is the MOST important task of the
project sponsor?

A.
Obtain funding for the project.

B.
Provide quality review of the deliverables.

C.
Provide leadership to the project team.

D.
Obtain resolution of the application development issues.

Explanation: