CompTIA Exam Questions

Which of the following is the Earned Value of this portion of the project?

A project manager has contracted with a landscaping service to complete the grounds work
on a new building. The landscaper provides the project manager with the following cost

estimate: $150 per hour, estimated time to completion=40 hours The landscaper has
completed 35 hours of work. Which of the following is the Earned Value of this portion of the
project?

A.
$6000

B.
$750

C.
$3000

D.
$5250