CompTIA Exam Questions

which of the following is the cost variance?

The project manager wants to report to the stakeholders to date project’s cost performance.
If the total of completed work to date is $200,000 and the actual cost is $210,000, which of
the following is the cost variance?

A.
5%

B.
5%

C.
$10,000

D.
$10,000