CompTIA Exam Questions

Which of the following documents would a project manager review to determine all the identified risk

Which of the following documents would a project manager review to determine all the identified
risks on a project?

A.
Risk matrix

B.
Risk register

C.
Risk response

D.
Risk baseline

Explanation: