Which of the following activities are associated with t… seenagape 8 years ago Which of the following activities are associated with the closing phase of a project? (Select TWO.) A. Risk mitigation B. Archiving of project documents C. Tracking of expenditures D. Lessons learned E. Quality assurance ← Previous question Next question →