CompTIA Exam Questions

Which of the following actions should the project manag…

The business stakeholder has been engaged late and has just had a chance to review the approved
requirements. Consequently, it has been identified that there are a number of gaps in the
requirements which are critical to the stakeholder’s business unit. Which of the following actions
should the project manager take?

A.
Initiate change control

B.
Follow communications plan

C.
Manage project quality

D.
Prepare a performance report