CompTIA Exam Questions

what the company?

Six months into development, the core team assigned to implement a new internal piece of software
must convene to discuss a new requirement with the stake holders. A stakeholder identified a missing
feature critical to the organization, which must be implemented. The team needs to validate the
feasibility of the newly introduced requirement and ensure it does not introduce new vulnerabilities to
the software and other applications that will integrate with it. Which of the following BEST describes what
the company?

A.
The system integration phase of the SDLC

B.
The system analysis phase of SSDSLCC. The system design phase of the SDLC

D.
The system development phase of the SDLC