CompTIA Exam Questions

This type of risk response is called:

A project team is reviewing the deliverables and identifies a deliverable no one on the team
has experience with. The lack of expertise is identified as a risk. The project manager
decides, as a workaround, to contract with a third party. This type of risk response is called:

A.
Transference.

B.
Avoidance.

C.
Monitor and Prepare.

D.
Acceptance.

Explanation: