CompTIA Exam Questions

This could have been avoided by using:

A project is having issues because the team is unclear what they should be doing and who
should be doing it. This could have been avoided by using:

A.
Acommunication plan.

B.
Change management.

C.
Arisk register.

D.
An issues log.