How many tapes would be required to perform a full restore if a complete failure occurred on Thursda

A full backup is performed every Sunday and incremental backups are performed daily Monday
through Saturday. How many tapes would be required to perform a full restore if a complete failure
occurred on Thursday before the incremental backup?

A.
2

B.
3

C.
4

D.
5

Explanation: