Which of the following documents should the project tea…

A program manager informs a project manager that a new, high-priority project has been approved
and will need the current project’s resources before the scheduled project close-date The project
team meets and determines that the project should be fast-tracked Which of the following
documents should the project team reference to fast-track the project? (Select TWO.)