CompTIA Exam Questions

After multiple service interruptions caused by…

After multiple service interruptions caused by

an older datacenter design, a company decided to migrate away from its datacenter. The company has successfully completed the migration of all datacenter servers and services to a cloud provider. The migration project includes the following phases:

Select

ion of a cloud provider

Architectural design

Microservice segmentation

Virtual private cloud

Geographic service redundancy

Service migration

The Chief Information Security Officer (CISO) is still concerned with the availability requirements of critical

company applications. Which of the following should the company implement NEXT?

A. Multicloud solution

B. Single-tenancy private cloud

C. Hybrid cloud solution

D. Cloud access security broker