After multiple service interruptions caused by
an older datacenter design, a company decided to migrate away from its datacenter. The company has successfully completed the migration of all datacenter servers and services to a cloud provider. The migration project includes the following phases:
Select
ion of a cloud provider
Architectural design
Microservice segmentation
Virtual private cloud
Geographic service redundancy
Service migration
The Chief Information Security Officer (CISO) is still concerned with the availability requirements of critical
company applications. Which of the following should the company implement NEXT?
A. Multicloud solution
B. Single-tenancy private cloud
C. Hybrid cloud solution
D. Cloud access security broker