A procedure that allows for the control of the project scope with respect to proposed changes to the

A procedure that allows for the control of the project scope with respect to proposed changes to
the plan is known as a:

A.
project charter.

B.
change control procedure.

C.
cultural change management procedure.

D.
procurement control plan.