Cisco Exam Questions

Which two values are possible for the maximum allocation of RC2? (Choose two

Two resource classes are defined as below:

RC1 and RC2 each have two member contexts
RC1 has a minimum allocation of 20% for all resources

Which two values are possible for the maximum allocation of RC2? (Choose two.)

A.
60%

B.
Unlimited

C.
30%

D.
80%