Which tasks is performed during the site readiness assessment gap analysis in the plan phase?

Which tasks is performed during the site readiness assessment gap analysis in the plan phase?

A.
Document Location of Legacy Equipment

B.
Document Bandwidth Requirements for each site

C.
Compare Systems Requirements specific to site survey

D.
Assess and Document infrastructure requirements for the proposed solution

E.
Determine if circuit can support required current calls