What is the correct order for performing the activities in the Change Management Service Component?

.What is the correct order for performing the activities in the Change Management Service Component?

A.
Originate, Evaluate, Accept and Schedule, Execute, Communicate, Close

B.
Originate, Schedule, Execute, Evaluate, Access, Communicate, Close

C.
Evaluate, Communicate, Accept, Schedule and Execute, Originate, Close

D.
Evaluate, Originate, Schedule, Execute, Access, Communicate, Close