Cisco Exam Questions

In the implement phase, project planning comprises which of the following tasks?

In the implement phase, project planning comprises which of the following tasks?

A.
Update and document logical and physical topology maps and serial numbers

B.
Confirm project and milestone dates, as well as project and cutover roles and responsibilities

C.
Install,configure, and provision core products

D.
Confirm deployment team, craft project plan,create communication and escalation plans