Developing a comprehensive detailed design that meets business and technical requirements involves w

Developing a comprehensive detailed design that meets business and technical requirements involves which of the following activities? Select exactly 1 answer(s) from the following:

A.
Correctly Implement Customer’s Wireless Policies in Wireless Solution Configurations

B.
Document and Design Infrastructure, Architecture, and Interfaces to Third-Party Applications

C.
Ensure All Necessary Hardware and Software Products Are Included in Design

D.
Identify Process to Follow if Issues Arise During Implementation