What is the most likely cause of CPU spikes, in light of the specified changes and assuming that no other chan

A new polling application was installed last week. This application monitors some of the routing
characteristics on your edge and aggregation devices. Since that time, you have been receiving
CPU threshold utlization alerts between 1 and 4 a.m. every day from multiple edge and
aggregation devices. What is the most likely cause of CPU spikes, in light of the specified changes
and assuming that no other changes happened in the network?

which of the following statements is correct?

An ISP operates a network that provides VPN service to enterprise customers. The customer uses
an MPLS network that is designed with redundant equal cost paths in the core. An enterprise
customer reported an increased latency and drop rate for some traffic flows from site A to site B.
The enterprise customer is connected to PE-A at site A and PE-B at site B.
If the latency problem is caused by a congested link in the core along a path from site A to site B,
which of the following statements is correct?

which action should you take to isolate the problem before escalating to the PSTN PTT carrier?

You are working in a service provider voice NOC supporting a national VoIP network. The network
underwent a capacity expansion that added voice bearer trunks to a newly deployed media
gateway. After the new trunks were configured and placed into live service, the service desk
began to receive complaints from end customers that their VoIP service is not working for certain
calls. The service desk is unable to resolve the problem and due to increasing troubles coming in,
they escalate to you.
Assuming that all physical layer option settings are verified to match carrier-provided
specifications, which action should you take to isolate the problem before escalating to the PSTN
PTT carrier?

Which missing item should be your biggest concern?

A rollout plan from engineering has been sent to the NOC for review. The plan approves
deployment of a new router model at the customer premises for all new service activations. The
certification lab has fully tested the new router and found no issues. As a NOC engineer, you
review the plan for completeness. An item is missing from the plan to deploy the new routers.
Which missing item should be your biggest concern?


Page 9 of 15« First...7891011...Last »