Refer to the exhibit.
48
What is the proper procedure to replace existing Fibre Channel switches with Cisco MDS switches to ensure minimum downtime? Select the best response.
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Shut down the whole environment and replace all the switches.
B.
Shut down one fabric at a time and replace only the shut down switches.
C.
Shut down individual switches and replace them one at a time.
D.
Bring in Cisco switches and unplug storage and servers from the old switches and plug them into the Cisco switches.