You want to copy data to a disaster recovery site using a native FC long distance solution. The
distance between the two sites is 200 km. The customer wants to ensure that the bandwidth of the
long distance link can be fully utilized. Which two additional factors must be considered? (Choose
two.)

PrepAway - Latest Free Exam Questions & Answers

A.
link speed

B.
Class of Service

C.
average payload size

D.
link cost