which of the following levels does sales and operations planning take place?
At which of the following levels does sales and operations planning take place?
Which of the following information is the key output of rough-cut capacity planning?
Which of the following information is the key output of rough-cut capacity planning?
What is the net requirement for X?
Part A is made from two Y’s and one X. An order is received for 50 A’s and there are 30 A’s
in stock. What is the net requirement for X?
which "pulls" production to the constraint for processing?
Which of the following terms refers to that which “pulls” production to the constraint for
processing?
Which of the following techniques deals with analysis and planning of logistics and manufacturing during vario
Which of the following techniques deals with analysis and planning of logistics and
manufacturing during various time periods?
Which of the following systems typically involves design while manufacturing is occurring?
Which of the following systems typically involves design while manufacturing is occurring?
What is the rated capacity for this work center?
A work center has 2 machines that are operated 16 hours a day for 5 days a week.
Historically, the utilization has been 85% and the efficiency 105%. What is the rated
capacity for this work center? (Rounded)
Which of the following scheduling techniques reduces manufacturing lead times?
Which of the following scheduling techniques reduces manufacturing lead times?
Earliest job due date is an example of:
Earliest job due date is an example of:
Which of the following techniques would address this need?
A manufacturer needs to monitor and balance the flow of work between work centers.
Which of the following techniques would address this need?