you need to gain the formal acceptance at project closure?

From whom do you need to gain the formal acceptance at project closure?

A.
The customer

B.
The qualify director

C.
Project management office

D.
Project manager

Explanation:
need to gain this formal acceptance at project closure from the customer and sponsor.