PMI Exam Questions

Who provides the inputs for the original estimates of activity durations for tasks on the project pl

Who provides the inputs for the original estimates of activity durations for tasks on
the project plan?

A.
Project sponsor

B.
Project manager

C.
Person responsible for project scheduling

D.
Person who is most familiar with the task