PMI Exam Questions

Which type of network diagram allows you to depict four types of dependencies (finish-to-start, fini

Which type of network diagram allows you to depict four types of dependencies (finish-to-start, finish-to-finish, start-to-start, and start-to-finish)?

A.
Precedence Diagramming Method (PDM)

B.
Gant Cnart Diagram (GCD)

C.
Dependency Diagramming Method (DDM)

D.
Arrow Diagramming Method (ADM)

Explanation:
The precedence diagramming method (PDM) supports finish-to-start, finish-to-finish, start-to-start, and start-to-finish dependencies.