PMI Exam Questions

Which tool or technique of the Define Activities proces…

Which tool or technique of the Define Activities process allows for work to exist at various levels of detail
depending on where it is in the project life cycle?

A.
Historical relationships

B.
Dependency determination

C.
Bottom-up estimating

D.
Rolling wave planning