Which tool or technique measures performance of the project as it moves from project initiation thro seenagape 11 years ago Which tool or technique measures performance of the project as it moves from project initiation through project closure? A.Resource leveling B.Parametric measuring C.Pareto chart D.Earned Value ← Previous question Next question →