PMI Exam Questions

which selection tool?

You are the project manager ofa project. During the process of selecting the seller, you reject one vendor because it does not have the manufacturing capability. This is an example of which selection tool?

A.
Weigthing System

B.
Screening system

C.
Seller rating system

D.
Expert judgement

Explanation:
Screening System Establish minimum performance requirement for one or more criteria.