Which Project Time Management process includes bottom-up estimating as a tool or technique? seenagape 11 years ago Which Project Time Management process includes bottom-up estimating as a tool or technique? A.Estimate Activity Resources B.Sequence Activities C.Estimate Activity Durations D.Develop Schedule ← Previous question Next question →