Which process uses occurrence probability and impact on…

Which process uses occurrence probability and impact on project objectives to assess the priority of identified
risks?

A.
Identify Risks

B.
Perform Qualitative Risk Analysis

C.
Plan Risk Management

D.
Perform Quantitative Risk Analysis