Which process uses occurrence probability and impact on project objectives to asses the priority of seenagape 11 years ago Which process uses occurrence probability and impact on project objectives to asses the priority of identified risks? A.Risk identification B.Qualitative Risk analysis C.Risk management planning D.Quantitative risk analysis ← Previous question Next question →