Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk R

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk
Responses?

A.
Identify Risks

B.
Plan Risk Management

C.
Perform Qualitative Risk Analysis

D.
Perform Quantitative Risk Analysis