Which process involves Monitoring, measuring, and taking corrective action?

Which process involves Monitoring, measuring, and taking corrective action?

A.
Executing processes

B.
Planning processes

C.
Controlling Processes

D.
Closing processes

Explanation:
Planning Processes: Approach to executing project.
Executing processes:Coordinating people and other resources.
Controlling Processes: Monitoring, measuring, and taking corrective action.
Closing processes: Formal product acceptance and end of project.