Which process involves determining, documenting, and managing stakeholders’ needs and requirem

Which process involves determining, documenting, and managing stakeholders’ needs and
requirements to meet project objectives?

A.
Collect Requirements

B.
Plan Scope Management

C.
Define Scope

D.
Define Activities