Which process involves defining, preparing, and coordinating all subsidiary plans and integrating th

Which process involves defining, preparing, and coordinating all subsidiary plans and
integrating them into a comprehensive plan?

A.
Direct and Manage Project Work

B.
Develop Project Management Plan

C.
Plan Quality Management

D.
Monitor and Control Project Work