PMI Exam Questions

Which process involves aggregating the estimated costs …

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

A.
Estimate Costs

B.
Estimate Activity Resources

C.
Control Costs

D.
Determine Budget