Which process group is for detailed resource assigments and responsabilities?

Which process group is for detailed resource assigments and responsabilities?

A.
Human resources management plan

B.
Project charter

C.
Aplan

D.
Project management plan

Explanation:
Develop Human Resource Plan: Planning, identifying, documenting, and assigning project roles, responsabilities, and reporting relationships to individuals groups.