Which process group contains the processes performed to finalize all activities? seenagape 10 years ago Which process group contains the processes performed to finalize all activities? A.Planning Process Group B.Executing Process Group C.Monitoring and Controlling Process Group D.Closing Process Group ← Previous question Next question →