Which process determines the risks that might affect the project? seenagape 9 years ago Which process determines the risks that might affect the project? A.Perform Qualitative Risk Analysis B.Identify Risks C.Plan Risk Management D.Perform Quantitative Risk Analysis ← Previous question Next question →