which process? seenagape 12 years ago Providing forecasts to update current cost and schedule information is a part of which process? A.Perform Integrated Change Control B.Direct and Manage Project Execution C.Monitor and Control Risks D.Monitor and Control Project Work ← Previous question Next question →